Our timeline

Pre-application consultation on the Boston Alternative Energy Facility has now ended and a Development Consent Order (DCO) application for the Facility was submitted to the Planning Inspectorate (PINS) in March 2021.  The application was accepted by PINS on 20th April 2021 and we anticipate an Examination to commence in early September 2021. During this Pre-examination stage, you will be able to register to become an Interested Party on the application by making a Relevant Representation to PINS.

The Examination will last up to six months and a decision on whether to grant the DCO will be made within six months after the close of the Examination.  A more detailed description of the process can be found here: The process | National Infrastructure Planning (planninginspectorate.gov.uk).